(14/6/2010-25/06/2010)
This unit is related with planning unit.Contruction unit will construct what already planned by planning unit.The flowchart of that process are given below

For all distribution capital projects financed via CAPEX, working paper has to be prepared and approved before implementation :
a)capital work authorizationform(CWA/BKKM)
b)Minor cost cost sheet(Mwcs/lkkk)
-for project cost les than RM 50 000
-does not involved MV network expansion/ change
-normally associated with service extension
A complete BKKM comprises of
a) Standard schedule of TNB
b) detail project description
c) location plan and As-fitted site plan
d) system schematic diagram complete with new proposalfor all MV expansion
e) Approved copy of MV technical proposal
f) Copy of supply application letter and initial load data submitted by consultant
g) copy of endorsed connection charge calculation letter
At the commercial affair, it responsible to the costumer account where all of the information of the billing accounts were organized and updated here. Also cut off electricity for non pay user were also done here, where team will respond to unpaid bill even though warning notice had been delivered. In the service and meter section the responsibility were installing new meter or upgrade the system. The job scope was to estimate, making cost sheet, services and install meter.
The SAVR are responsible to fix the end connections from the TNB Distribution supply cables to the consumer’s meter. This section basically receives the electrical fixing infrastructure.
Basically, this section handles, maintains and repairs the Low Voltage (LV) fixings in the area so:
1. The supply is stable and safe for use.
2. Preventing supply disruptions and faults on the fixings
3. Maximizes the lifespan of the fixings.
This is done via a routine maintenance schedule such as:
1. Patrolling and making visual checks on the span of overhead cables
2. Cleaning/cutting tree trunks which are in the way of overhead cables every three months
3. Numbering/renumbering poles that carry overhead cables
4. Monitoring/Taking load readings from low voltage users
5. Redistributing and splitting the supply from overloaded energy suppliers
6. Tightening contacts on the SAVR fixings
7. Changing old wooden and steel poles with newer concrete poles.
8. Changing old bare aluminum cables with ABC cables for locations that are problematic for the bare cables.
Other jobs include doing operations, switching, isolating and commissioning SAVR fixings to repair faults and maintenance purposes. If needed, this section can request for additional equipment from the Bachok Open Store yard, where most of the stuff is stored and sent back to be scrapped.
(5/4/2010-14/4/2010) substation
In the electrical distribution network, a sub-station has many components such as circuit breaker, transformer, and switches, fuses which must be housed properly to ensure continuous and reliable service. According to construction of sub-station, several factors need to be taken for the construction such as location and load demand
There have 4 types of sub-stations in electrical distributions network
Indoor substation
Outdoor substation
Pole-mounted substation (H-pole)
Compact substation
Components in substation
Switchgears – not available in H-pole.
Ring Main Unit – located in PPU only.
Transformers
Protections
Protection Relays and Vacuum Circuit breaker (VCB) – located in PPU only.
Transformer Fuses
Isolating Switch – Located in H-Pole only
Pin Insulator – Located in H-Pole only
Low Voltage Fuses – Located in H-Pole only
Lightning Arresters – Located in H-Pole only
Earthling
Underground Cables
PILC
XLPE
Distribution Boards
Low Voltage Distribution board (LVDB)
Feeder Pillar
Substation work
Done once per 3 months
Done by seeing, hearing, smelling and feeling the substation and its equipment to see if there is anything wrong with the particular substation
If there were any defect, report to Authorized Person (AP) for corrective maintenance.
Done once every 6 months
Take substation data, load reading
Work including cleaning and repairing inside and outside substation such as cut grass, throw rubbish, repairing broken gate and take LV current
Data reading at LVDB.
Done once every 18 months
Full maintenance from top to bottom, involving all of the equipment inside and outside the substation
Done by either the Substation Team or an outside contractor
Among the list of things to do include servicing the LV distribution board (LVDB), servicing the switchgears and servicing the transformers